|
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain. Port Washington, WI 53074
April 14, 2005
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, County Board Chairman, Brooke,
County Administrator Tom Meaux, Peter Waldkirch, and Mary Sampont.
Supervisor Miller arrived at 8:40 A.M.
Absent: Supervisor Boesch.
Also present: Highway Commissioner Dreblow.
Chairman Grosklaus indicated that the meeting has been properly noticed.
Motion to accept minutes from March 3, 2005 meeting made by Mr.
Grosklaus, seconded by Mr. Brooks. Motion carried.
Lasata received two bids for installing air-conditioning for the
Maintenance office and Housekeeping. The project has been budgeted.
Major Heating Cooling $10,675.00
Brenner Corporation $ 9,245.00
Motion to award the bid to Brenner Corporation for $9,245.00 made by Mr.
Uselding, seconded by Mr. Brooks. Motion carried.
Discussion regarding whether to proceed with redoing handicap entrance at
Administration Center. Motion to table discussion by Mr. Uselding, seconded
by Mr. Grosklaus. Motion carried.
Discussion regarding the Jail slab repair. Earth Tech has identified what
the problem is. They will prepare the bid documents for $5,000.00. They have
provided three options.
Option 1 – slab & wall removal and recompaction
$15,000 - $20,000
Option 2 – pressure grouting "mud jacking" (may need to be repeated in 5
to 10 years)
$10,000 - $15,000
Option 3 – self-leveling topping (this was previously done)
not recommended
Peter will contact the Insurance Company to see if this would be covered.
Motion to have Earth Tech proceed with study for $5,000.00 by Mr.
Uselding, seconded Mr. Brooks. Motion carried.
Lasata received an estimate of $30,000.00 to remodel Infirmary and put in
a Medicine Room. Motion to put out for bid made by Mr. Uselding, seconded
Mr. Grosklaus. Motion carried.
Discussion regarding the former jail. Mr. Meaux received 4 proposals
regarding the RFP on the former jail.
Haag Muller, Inc. No bid
Barrientos Design & Consulting LLC $ 8,600.00
Venture Architects $20,000.00
Kubala Washatko Architects $40,520.00
Mr. Meaux presented the Committee with the two most favorable options.
Motion to award bid to Barrientos Design & Consulting, in the amount of
$8,600.00, made by Mr. Uselding, seconded by Mr. Brooks. Motion carried.
Other business – sidewalk replacement on Washington Street, across from
Fire Department. A temporary fix was made in 2004. Recommendation to table
and budget for 2006. Mark Banton, Highway County Surveyor, will provide
different scenarios.
Motion to adjourn made by Mr. Uselding, seconded by Mr. Miller. Motion
carried. Meeting adjourned at 8:55 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
March 3, 2005
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Boesch, Uselding, County Administrator
Tom Meaux, Peter Waldkirch, and Mary Sampont.
Absent: Supervisors Eckert and Miller.
Also present: Dennis Riley, Lakeside Development Co.; Kris Halbig-Ziehm,
Ozaukee Press; and Dan Benson, Journal-Sentinel.
Chairman Grosklaus indicated that the meeting has been properly noticed.
Motion to accept minutes from February 3, 2005 meeting made by Mr.
Boesch, seconded by Mr. Uselding. Motion carried.
Peter informed the Committee of two upcoming trade shows being held at
McCormick’s Place in Chicago. The National Manufacturing Show from March
7-9,2005 and the Total Facility Management Show from April 20-22. The
Committee gave the approval for Peter to attend these shows and to include 1
extra person to attend with him.
Peter shared with the Committee the bid proposals for the
air-conditioning project in Main Control. He told them he accepted the low
bid of $6,005.82 from Major Systems, Inc. They will be installing the
identical unit that Johnson Controls had originally proposed at a cost of
$2,588.00 less than Johnson Controls.
Lasata has requested approval to renovate the Medication/Treatment Room.
The estimated cost is $25,000.00, with the money in the budget. The project
is currently out on bid. Motion to proceed with the project made by Mr.
Uselding, seconded by Mr. Boesch. Motion carried.
Discussion regarding the former Jail. A draft was presented to request a
proposal of architectural services for the evaluation of the former jail and
provide an assessment of the facility to the County. Motion to proceed with
request made by Mr. Uselding, seconded by Mr. Boesch. Mr. Riley explained
that this is what he proposed to do, but at his expense. If an outside party
would be considered for occupying the building, they would reimbursement
Lakeside Development for their services. The Committee feels that since it
is still County owned property, it is our responsibility to proceed with
obtaining a feasibility report on the structure.
Discussion regarding handicap access to Administration and Justice
Centers. Peter informed the Committee that according to the State Building
Inspector, the County is in compliance with access to the buildings. Peter
did, however, obtain a bid to upgrade the Administration Center access to
the building. He will contact Mark Banton from Highway to assess the
proposed upgrade. Peter has also received a proposal to install an automatic
door opener at the Justice Center. Mr. Meaux suggested Peter hold off on
this pending a report from the U.S. Marshall regarding the Security Study
that was done in January.
The Lease for the Public Defenders has expired 2/28/05. They occupy two
small offices in the basement of the Historical Building. The Department of
Administration has contacted Peter and they will renew the contract with a
3% increase for 1 year with the option of 2 additional years at an
additional 3% per year. Motion to accept the proposal made by Mr. Boesch,
seconded by Mr. Uselding. Motion carried.
Motion to adjourn made by Mr. Boesch, seconded by Mr. Uselding. Motion
carried. Meeting adjourned at 8:40 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
February 3, 2005
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Boesch, Eckert, Uselding, Miller, County
Administrator Tom Meaux, Peter Waldkirch, and Mary Sampont.
Also present: John Kuhnmuench, Human Resources Director; Kathy Schaefer,
United Way; Joan Kojis, Dept. of Human Services; Joellen Wichmann, Salvation
Army; Dennis Riley & Tom Zabjek, Lakeside Development Co.; Erica Dimmett,
Advocates; Kimberly McCulloch, Volunteer Center of Ozaukee County; Ann
Conners, Dept. of Human Services Fiscal Unit; Dan Benson, Journal-Sentinel;
Kris Halbig-Ziehm, Ozaukee Press.
Chairman Grosklaus indicated that the meeting has been properly noticed.
Motion to accept minutes from January 6, 2005 meeting made by Mr. Boesch,
seconded by Mr. Uselding. Motion carried.
Discussion regarding a feasibility study of the former jail. Lakeside
Development Company is proposing a six-month time period to perform due
diligence, environmental study and feasibility studies. Upon completion, a
complete report would be submitted to the County.
Discussion regarding using the former jail as a homeless shelter was
presented with representatives from United Way, Salvation Army and Dept. of
Human Services. It was noted by Joan Kojis that there were 125 detentions in
2004 at a cost of $1,000/per day, per person for Chapter 51/55.
Motion to table further discussion regarding Lakeside Development Company
and Salvation Army proposals until the March, 2005 Buildings Committee
meeting, made by Mr. Uselding, seconded by Mr. Eckert. Motion carried.
Kimberly McCulloch, Volunteer Center of Ozaukee County, made a request to
use the Justice Center parking lot on Saturday, August 13, 2005. They would
provide portable restrooms, tents, stage, etc. for the festivities. The
County would only need to provide a hose for water. Motion to approve use of
the Justice Center parking lot, pending approval from the City of Port
Washington made by Mr. Miller, seconded by Mr. Boesch. Motion carried.
Ann Connors, Department of Social Services Fiscal Unit, made a request
that the Fiscal Unit of the combined Departments of Social Services and
Community Programs (Department of Human Services) relocate to the 3rd
floor office area formerly occupied by the Finance Department. The only cost
would be hookup of telephones and computers. Motion to approve relocation
made by Mr. Eckert, seconded by Mr. Uselding. Motion carried.
Discussion regarding Handicapped entrances for Administration and Justice
Centers. There is an automatic door installed at the Administration Center,
but there it is hard to maneuver at the top of the ramp by the support
pillar. It was suggested that Peter look into alternative ways for access to
the building. There is no automatic door access at the Justice Center. Peter
received an estimate of $3,989.00 and would like to obtain additional quotes
not to exceed said amount. He will also check into grant options for the
Justice Center.
Discussion regarding installing 2 air-conditioning units in Main Control.
A proposal has been received in the amount of $8,593.00. Request for
additional bids will be published. The money will be out of the Jail
Assessment fund. Motion to approve obtaining additional bids not to exceed
$8,593.00, made by Mr. Eckert, seconded by Mr. Boesch. Motion carried.
Invoice for approval:
KONE, Inc. $21,679.20
Motion to pay invoice from KONE, Inc. in the amount of $21,679.20, made
by Mr. Uselding, seconded by Mr. Miller. Motion carried.
Motion to adjourn made by Mr. Eckert, seconded by Mr. Boesch. Motion
carried. Meeting adjourned at 9:07 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
January 6, 2005
The Buildings Committee met at the Highway Dept. at 8:30 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Boesch, Miller, and Peter
Waldkirch.
Absent: Supervisor Eckert.
Motion to approve minutes of December 9, 2004 meeting made by Mr. Boesch,
seconded by Mr. Miller. Motion carried.
Discussion regarding Handicap Access to Justice Center and Administration
Center. Peter will look into accessibility issue and report at next month’s
meeting.
Discussion regarding Elevator #2 which seems to have an excess amount of
breakdowns. The last few times Elevator #2 broke down was because of bad
rollers. After this last time, we had the Elevator Company replace all rollers
in the car. We will monitor the unit to see if this takes care of most of the
problems.
Motion to pay invoices for payment for Lasata Elevator Renovation project
made by Mr. Uselding, seconded by Mr. Boesch. Motion carried.
KONE $ 1,736.00
J. Miller Electric, Inc. 4,556.30
17,220.25
$23,512.55
Motion to adjourn meeting made by Mr. Miller, seconded by Mr. Boesch.
Meeting was adjourned at 9:00 A.M.
Respectfully submitted,
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
December 9, 2004
The Buildings Committee met at the Highway Dept. at 8:45 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Miller, Peter Waldkirch, and Mary
Sampont.
Absent: Supervisors Boesch and Eckert.
Motion to approve amended minutes of November 11, 2004 meeting made
by Mr. Uselding, seconded by Mr. Miller. Motion carried.
Motion to approve transfer of Building Committee duties to Highway
Committee pending approval by Highway Committee and County Board as a whole,
made by Mr. Miller, seconded by Mr. Uselding. Motion carried.
Motion to adjourn meeting made by Mr. Miller, seconded by Mr. Uselding.
Meeting was adjourned at 8:50 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
Port Washington, WI 53074
November 11, 2004
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Eckert, Peter Waldkirch, and Mary
Sampont.
Absent: Supervisors Boesch and Miller.
Motion to approve minutes of October 14, 2004 meeting made by Mr. Eckert,
seconded by Mr. Uselding. Motion carried.
Peter advised the Committee that the cost of training for asbestos removal
would be $500.00 per person. Motion to send two people for training for
identification of asbestos only, made by Mr. Uselding, seconded by Mr. Eckert.
Motion carried.
The south side of Building #4 is badly deteriorating. Peter received a
proposal of $9,350.00 to do repair work to building. Motion to accept the
proposal from Geidel Construction to proceed with the repairs, not to exceed
$9,350.00, was made by Mr. Uselding, seconded by Mr. Eckert. Motion carried.
An informational item only, Peter had a contractor look at the doors on the
west side of the Beef/Hog building. These doors will need to be replaced. He
will be getting more than one proposal.
A request was received from the Port Washington Junior Woman’s Club to
redecorate the Observation Room located in the Social Services Department.
There would be no cost to Social Services or Ozaukee County. This is a donated
project funded through the Port Washington Junior Woman’s Club. Motion to
accept project made by Mr. Uselding, seconded by Mr. Eckert. Motion carried.
Motion to adjourn meeting made by Mr. Boesch, seconded by Mr. Uselding.
Meeting was adjourned at 8:20 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
October 14, 2004
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Boesch, Eckert, Peter Waldkirch,
and Mary Sampont.
Absent: Supervisor Miller.
Also Present: Mary DeLuca, Public Health Dept.
Motion to approve minutes of September 2, 2004 meeting made by Mr. Uselding,
seconded by Mr. Grosklaus. Motion carried.
Peter informed the Committee that the elevator project at Lasata is
completed. The final payment of $21,679.22 is being withheld pending receipt
of AIA documents, maintenance manuals, as-built drawings, wiring diagrams,
etc. Several attempts have been made to obtain this information, but with no
luck as of yet.
Mary DeLuca explained to the Committee the need for the door being put in
the wall. Motion to approve the construction made by Mr. Boesch, seconded by
Mr. Eckert. The vote was 3 ayes, 1 nay. Motion carried.
Peter had a scrap dealer come in to check out the possibility of steel
removal from the former jail. The contractor would expect us to pay him and he
would keep the metal. The County is looking into the possibility of training 2
employees in asbestos removal. Motion to do asbestos testing made by Mr.
Uselding, seconded by Mr. Eckert. Motion carried.
After discussion regarding the possible merging of Buildings Committee and
Highway Committee, a motion was made by Mr. Uselding, seconded by Mr. Boesch,
to move forward with the consolidation of the two committees. Motion carried.
Motion to adjourn meeting made by Mr. Boesch, seconded by Mr. Uselding.
Meeting was adjourned at 8:37 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
Port Washington, WI 53074
September 2, 2004
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Boesch, County Administrator Tom
Meaux, Peter Waldkirch, and Mary Sampont.
Absent: Supervisors Eckert and Miller.
Also Present: Bob Dreblow, Highway Director and Mark Banton, County
Surveyor.
Motion to approve minutes of August 5, 2004 meeting made by Mr. Uselding,
seconded by Mr. Boesch. Motion carried.
Peter has contacted Earth Tech to do the testing for the Jail Floor for a
cost of $5,000.00. This is the estimate for work to be completed on the
weekend. Motion to accept the bid made by Mr. Uselding, seconded by Mr.
Boesch. Motion carried. Tom Meaux will talk to Judge McCormick about
scheduling the work to be done during the week. Peter will check if there
would be a savings in cost if work is done during the week versus the weekend.
It is estimated that the scope of work would take 1 1/2 days to complete.
Received three bids for resealing of driveway at Advocates.
N/R Asphalt, West Bend $750.00
Cashin Asphalt, Cedarburg $795.00
MAC, Inc., Milwaukee $900.00
Motion to accept bid from Cashin Asphalt for $795.00, made by Mr. Uselding,
seconded by Mr. Boesch. Motion carried. Cashin Asphalt will be applying two
coats, versus one coat by the other two proposals.
The Nurses’ Office is requesting that a door be installed between the break
room and conference room. This entails going through a block wall. Discussion
has been tabled.
The sidewalk on the North side of the Administration Center needs to be
replaced. The City of Port Washington recently mud jacked several sections
causing the sidewalk to be higher than the aggregate between the sidewalk and
curbing. Mark Banton proposed removing the current sidewalk and aggregate and
replacing the entire area with 5 inches of cement making it flush with the
curb. Highway Department would do the work and they would also cut out a
section of the curb in front of the main entrance to prevent buildup of water
flowing towards the steps. The estimated cost is $8,000.00. Motion to approve
Highway Department replacing the sidewalk made by Mr. Uselding, seconded by
Mr. Boesch. Motion carried.
Discussion regarding consolidation of Buildings and Highway Committees is
doable per Corporation Counsel. At this time the general consensus is
favorable for consolidation. The Buildings Committee will refer until the next
full committee meeting for discussion and vote. It has been requested that the
proposal be presented to the committee members prior to the next meeting.
Bob Dreblow reported that the final estimated costs for replacing the
parking lot on the South side of the Administration Center will be $23,000.00.
Motion to adjourn meeting made by Mr. Boesch, seconded by Mr. Uselding.
Meeting was adjourned at 8:40 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
Port Washington, WI 53074
August 5, 2004
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding Eckert, Boesch, Miller, Peter
Waldkirch, and Mary Sampont.
Also Present: Lt. Gerald Ebert, Sheriff’s Dept.; Bill Stolte, Emergency
Management Director; and Bob Dreblow, Highway Director.
Motion to approve minutes of July 22, 2004 meeting made by Mr. Eckert,
seconded by Mr. Miller. Motion carried.
Peter informed the Committee of the new procedure regarding alarms from the
North/South Tower sites. On June 26 the North Tower A/C unit failed. 2 new
air-conditioners will be installed. Maintenance Dept. will respond to alarms
immediately.
Lt. Ebert presented bids for the new Security System for the Jail/Justice
Center. The money will be coming from Homeland Security. There were 3
responses out of 5 contacts for bids received.
Stanley Security $43,958.74
Johnson Controls $62,309.50
Toepfer Security $77,920.00
Motion to accept the low bid from Stanley Security for $43,958.74 was made
by Mr. Uselding, seconded by Mr. Eckert. Motion carried. Contract will be
awarded to Stanley Security.
Peter reported that a portion of the roof above the garage at Lasata, 2,500
sq. ft. will need to be replaced. It is going to cost between $10,000 -
$15,000. The request for bids is being published and the Committee should have
the bids at the next meeting.
The Lasata elevator renovation project is completed. There is $2,097.00
left in the project budget. Ralph Luedtke is waiting for the final state
inspection.
Due to the number of low spots in the South parking lot at the
Administration Center, it was recommended that the lot be redone this year,
instead of just patching specific areas. Highway Dept. is doing the work at
this time. They installed 75 feet of drain tile along the wall on Grand
Avenue. They also dug down 2 feet and put stone in to make a stable bed for
the blacktop. Bob Dreblow reported the paving will be done on Monday, the
second coat put down on Tuesday, and striping will be done on Wednesday.
Motion to adjourn meeting made by Mr. Boesch, seconded by Mr. Uselding.
Vote was 4 ayes, 1 nay. Meeting was adjourned at 8:18 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
July 22, 2004
The Buildings Committee met at the Highway Dept. at 7:30 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Eckert, Boesch, Miller, Peter Waldkirch,
and Mary Sampont.
Also Present: County Administrator Meaux.
Absent: Supervisor Uselding
Peter passed out a new policy regarding the Radio Tower Maintenance policy
as requested by Technology Resources. Discussion has been tabled until the
next Building Committee meeting.
Peter presented the Committee with the proposed 2005 budget to be submitted
to Finance Committee by August 2, 2004. After much discussion, a motion to
pass the proposed budget was made by Mr. Eckert, seconded by Mr. Boesch.
Voting was 3 ayes, 1 nay. Motion carried.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
July 8, 2004
The Buildings Committee met at the Highway Dept. at 8:00 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Eckert, Boesch, Miller, Peter
Waldkirch, and Mary Sampont.
Also Present: County Administrator Meaux and Highway Commissioner Bob
Dreblow.
Minutes of the May 18, 2004 meeting were reviewed. Motion by Mr. Eckert,
seconded by Mr. Uselding, to approve the minutes as received. Motion carried.
Peter consulted with Bob Dreblow regarding the problem with the Jail floors
shifting. Bob has contacted a company to come and do 2 borings. The first is
for a soil testing to determine the types of soil under the building. The
second is to determine the soil compaction. The estimated cost of the borings
is $2,500.00. The total cost of borings and a report with methods of repair is
estimated at $5,000.00. Prior to scheduling the soil borings, Peter and Tom
will meet with the Judges to determine the best time to perform this
procedure. Motion to proceed with borings and a complete report, with total
cost not to exceed $5,000.00, was made to Mr. Eckert, seconded by Mr. Uselding.
Motion carried.
Peter presented the 2005 proposed budget to the Committee along with the
recommended increases for the upcoming year. For the Administration Center
budget, the window replacements were eliminated.
Peter also suggested that once a new director is appointed for Advocates,
the Committee should take a trip out there to acquaint the Director with the
Committee as a whole.
Motion to adjourn by Mr. Uselding, seconded by Mr. Eckert. Motion carried.
Meeting adjourned at 8:40 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
May 18, 2004
The Buildings Committee met at the Justice Center in Room 240 at 8:30 A.M.
The meeting was called to order by Chairperson Grosklaus.
Present: Supervisors Grosklaus, Uselding, Eckert, Boesch, Miller, Peter
Waldkirch, and Mary Sampont.
Also Present: Lt. Ebert, Chief Knowles, County Administrator Meaux.
Minutes of the April 12, 2004 meeting were reviewed. Motion by Mr. Uselding,
seconded by Mr. Eckert, to approve the minutes as received. Motion carried.
Chief Knowles presented the Committee with the electronic upgrade in the
Jail/Main Controls. This project has been approved by the Law Enforcement
Committee and was presented to the Buildings Committee as a courtesy to keep
them informed of what changes are taking place in the building. $150,000.00
has been budgeted for this project, however, the lowest proposal came in about
$9,000.00 over. There is money in the Jail Assessment fund and the Maintenance
Dept. will request an additional $10,000.00 be approved to allow for
incidental costs. It would also support the cost of moving the security
Pass-thru Window, construction of new millwork, monitor supports, possible
electrical upgrades, new flooring if needed once the old system has been
removed. This project should start later this year. Motion to approve by Mr.
Eckert, seconded by Mr. Uselding. 4 ayes, 1 abstained. Motion carried.
Lt. Ebert presented the Committee with information regarding the purchase
of a new Security Card System. He has received information regarding the
system from Johnson Controls and Com-Tec. It is hopeful the money will come
from Homeland Security funds. Discussion regarding this project has been
tabled until the final bids have been received.
A request has been made by the Livestock Association to the Committee to
pay $600.00 for concrete for new hog pens that will be installed in the
Beef/Swine Barn on the north side. It was noted that the labor has been
donated by members from the 4-H Livestock Association to lay the concrete.
Motion to approve by Mr. Miller, seconded by Mr. Uselding. Motion carried.
A request has been received by a private entity to use the Auditorium in
the Administration Center one night a week for approximately 3 hours for a
dance group. They would be willing to contribute $20.00 per night to help
defray costs. Motion to reject the request by Mr. Eckert, seconded by Mr.
Uselding. 3 ayes, 2 nays.
Peter informed the Committee that the Youth Building needs to be repainted
this year. We have received two estimates as follows:
B & J Painting, Inc. $2,120.00
Dave Kitzki Painting Service $4,700.00
The Committee previously approved the request that the building be
repainted as a cost not to exceed $3,000.00.
Invoice for Lasata Elevator project:
KONE, Inc. $15,378.30
Payment #7
Motion to approve payment of invoice for $15,378.30, made by Mr. Uselding,
seconded by Mr. Eckert. Motion carried.
Peter also informed the Committee that the new safety switch required by
the State will be installed in the elevators around June 8.
A request was made to put Handicapped parking spaces with a curb cutout, in
the front of the Administration Center. Peter contacted the Public Works
Director for the City of Port Washington. He said it was a possibility, but
there is already accommodations at the corners with reserved parking for
handicapped vehicles. Motion to reject the request was made by Mr. Eckert,
seconded by Mr. Miller. Motion carried.
The next scheduled dates for the Buildings Committee will coincide with the
Highway Department meetings as follows:
Friday, June 11
Thursday, July 8
Thursday, August 12.
The Buildings Committee will meet at 8:30 A.M. at Highway Department.
Motion to adjourn by Mr. Boesch, seconded by Mr. Uselding. Motion carried.
Meeting adjourned at 9:22 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
The Following Minutes Have Not Yet Been Approved By The Committee To Which
They Pertain.Port Washington, WI 53074
April 12, 2004
The Buildings Committee met at the Administration Center in Room 118 at
8:30 A.M.
The meeting was called to order by Chairperson Lampert.
Present: Supervisors Lampert, Egelhoff, Grosklaus, Uselding, County Chair
Sandy Wirth, Jason Dzwinel, Former County Chair Leroy Bley, Peter Waldkirch,
and Mary Sampont.
Absent: Supervisor Eckert.
Minutes of the March 17, 2004 meeting were reviewed. Motion by Mr. Egelhoff,
seconded by Mr. Grosklaus, to approve the minutes as received. Motion carried.
Peter received two estimates for repainting the Youth Building at the
Fairgrounds.
B & J Painting, Inc. $2,120.00
Dave Kitzki Painting Service $4,700.00
Motion by Mr. Egelhoff, seconded by Mr. Grosklaus to go ahead with
repainting the building, not to exceed $3.000.00.
Peter received a change order for the Lasata Elevator project for
$20,877.00. The State Elevator Inspector informed Ralph Luedtke that emergency
power transfer switching equipment must be installed in all elevators in case
of fire or power failure. This must be done to meet state codes. Motion to
approve the change order made by Mr. Grosklaus, seconded by Mr. Egelhoff.
Motion carried.
Invoice for Lasata Elevator project:
KONE, Inc. $22,103.55
Payment #6
Motion to approve payment of invoice for $22,103.55, made by Mr. Uselding,
seconded by Mr. Grosklaus. Motion carried.
Invoice for Cedarburg Highway Vehicle Storage building:
W. B. Corp. $ 1,019.00
Motion to approve payment subject to approval from Highway Commissioner
Dreblow, made by Mr. Uselding, seconded by Mr. Grosklaus. Motion carried.
Jason Dzwinel presented information to the Committee regarding the Historic
Structures Report study. In order for Ozaukee County to apply for various
grants, there has to be a study to do an analysis of the Historical Building.
There will be no County dollars involved in this study. Ozaukee County will
receive grant dollars for the full amount of $43,970.00. Approval of the
study, pending receipt of the money, made by Mr. Egelhoff, seconded by Mr.
Grosklaus. Motion carried.
Chairman Lampert extended his thanks to the Building Committee for their
support during his tenure as Board Chair and during his 14 years on the
Building Committee.
Motion to adjourn by Mr. Egelhoff, seconded by Mr. Grosklaus. Motion
carried. Meeting adjourned at 9:05 A.M.
Respectfully submitted,
Mary M. Sampont, Secretary
Table of
Contents
Port Washington, WI 53074
March 17, 2004
The Buildings Committee met at the Administration Center in Room 118 at
8:30 A.M.
The meeting was called to order by Chairperson Lampert.
Present: Supervisors Lampert, Egelhoff, Grosklaus, Eckert, Uselding, County
Clerk Mary Marchese, Jason Dzwinel, Peter Waldkirch, and Mary Sampont.
Minutes of the February 17, 2004 meeting were reviewed. Motion by Mr.
Eckert, seconded by Mr. Grosklaus, to approve the minutes as received. Motion
carried.
Co. Clerk Marchese explained how the move came about for the main
Switchboard. The Information Center has been relocated to the County Clerk’s
office. With the work being in-house, there is an estimated savings of
approximately $10,000.00. Jason Dzwinel proposed a new sign directory layout
for the Administration Center. Peter will work with him on getting proper
signage.
The 3rd elevator at Lasata has been completed and the State
inspected and released it into service on Monday, March 15, 2004. The last
elevator should be completed late March or early April. There is some concern
regarding the control of the elevators during a power outage. Performance
Elevator Consultants will check into this and advise Ralph of their findings.
Peter reported that a Maintenance Supervisor has been hired for Lasata. He
is Dale Wedde from Cedarburg, and has experience in the Health Care area. He
has extensive knowledge regarding the HVAC systems, plumbing, electrical, etc.
fields.
Invoice for Lasata Elevator project:
KONE, Inc. $5,124.15
Payment #5
Performance Elevator Consulting, LLC 2,250.00
Motion to approve payments of invoice for $7,374.15, made by Mr. Egelhoff,
seconded by Mr. Eckert. Motion carried.
Motion by Mr. Egelhoff, seconded by Mr. Grosklaus to adjourn. Motion
carried. Meeting adjourned at 9:05 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
Port Washington, WI 53074
February 17, 2004
The Buildings Committee met at the Justice Center in Room 240 at 8:30 A.M.
The meeting was called to order by Chairperson Lampert.
Present: Supervisors Lampert, Egelhoff, Grosklaus, Eckert, Tom Meaux,
County Administrator; Bill Knight, Parks Commissioner; Peter Waldkirch, and
Mary Sampont.
Absent: Supervisor Uselding.
Minutes of the January 21, 2004 meeting were reviewed. Motion by Mr.
Egelhoff, seconded by Mr. Eckert, to approve the minutes as received. Motion
carried.
The Port Washington Soccer Club has requested that signs be put up
identifying the soccer fields on the land adjacent to the Justice Center.
There would be a large identification sign placed on Spring Street side and a
secondary sign placed on Sunset Road side. Motion to approve the signs made by
Mr. Eckert, seconded by Mr. Egelhoff. Motion carried.
The 6 inch water line at Lasata has been abandoned; therefore this is a
dead issue.
We were informed that Stubenrauch Architects has closed their doors. They
were the architectural firm for Lasata. Motion to terminate their contract
made by Mr. Grosklaus, seconded by Mr. Egelhoff. Motion carried. A motion to
pay Performance Elevator Company $3,750.00 to complete the project was made by
Mr. Grosklaus, seconded by Mr. Eckert. Motion carried.
Park Commission Bill Knight has requested that he have carpeting installed
in the office area he will be occupying shortly. Motion to approve carpeting,
with the cost not to exceed $1,500.00, was made by Mr. Grosklaus, seconded by
Mr. Egelhoff. Motion carried.
Invoice for Lasata Elevator project:
J. Miller Electric, Inc. $ 1,855.60
Motion to approve payment of invoice for $1,855.60, made by Mr. Eckert,
seconded by Mr. Grosklaus. Motion carried.
The Buildings Committee then proceeded to the newly relocated Corporation
Counsel and Veterans’ Service offices.
Motion by Mr. Grosklaus, seconded by Mr. Egelhoff to adjourn. Motion
carried. Meeting adjourned at 8:55 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents
Port Washington, WI 53074
January 21, 2004
The Buildings Committee met at the Administration Center in Room 118 at
8:30 A.M.
The meeting was called to order by Chairperson Lampert.
Present: Supervisors Lampert, Egelhoff, Grosklaus, Eckert, Tom Meaux,
County Administrator; County Board Chairman Gus Wirth; Peter Waldkirch, and
Mary Sampont.
Absent: Supervisor Uselding.
Minutes of the December 17, 2003 meetings were reviewed. Motion by Mr.
Egelhoff, seconded by Mr. Grosklaus, to approve the minutes as received.
Motion carried.
At the last Lasata Committee meeting, Peter was given the additional duties
of overseeing the buildings maintenance and housekeeping staffs for the Lasata
buildings. Lasata will be hiring a Building Supervisor who will report to
Peter.
Peter informed the committee of a request from Jeff Schmidt to put
carpeting in the back hallway in the Clerk of Courts office and Judges’
chambers. It was reported that several employees have slipped on the tile
floor and Jeff feels it necessary to have it carpeted as a safety issue. Peter
received a preliminary estimate of $4,568.00. Motion to approve the carpeting
by Mr. Egelhoff, seconded by Mr. Grosklaus. 2 ayes, 1 nay, 1 abstain. Motion
carried. Peter will notify Jeff of the approval.
Invoice for Lasata Elevator project:
Kone, Inc. Payment #2 $ 97,061.76
Payment #3 21,794.40
Payment #4 16,527.15
TOTAL $135,383.31
Motion to approve payment of invoices for $135,383.31 made by Mr. Egelhoff,
seconded by Mr. Eckert. Motion carried.
Peter also reported that the door installed for Emergency Management has
been completed.
The Committee then proceeded to tour the newly relocated Finance Department
and the prospective Parks offices.
Next meeting to be held on Tuesday, February 17, 2004 at the Justice Center
in Room 43.
Motion by Mr. Egelhoff, seconded by Mr. Grosklaus to adjourn. Motion
carried. Meeting adjourned at 9:26 A.M.
Respectfully submitted,
Mary M. Sampont
Secretary
Table of
Contents |