|
DRAFT
July 22, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 9:00 a.m. Present were committee
members Kaul, Hilber, Grosklaus and Kletti, Commissioner Dreblow,
Office Manager Carroll and Administrator Meaux. Scott Solverson,
representing Earth Tech was also in attendance.
Moved by Kletti and second by
Grosklaus to approve the minutes of the July 8, 2004 meeting as
printed. All members present voting aye, the motion was adopted.
The committee agreed to change the order of the agenda and to address
the CTH T and CTH W intersection reconstruction project.
Solverson reviewed the project estimate
($457,528.40), the accepted bid ($340,883.51) and the actual cost
($471,942.90). He explained the cost over runs and displayed a map
showing the areas where additional base excavation was needed. The
contract called for the project to be complete as of June 28, 2004.
Buteyn-Peterson has requested a time extension for weather and the
increased scope of services. The Highway Committee believes that there
were days that Buteyn-Peterson could have been working but elected not
to work. Buteyn-Peterson agreed to contract modifications without a
request for additional workdays. Solverson will request Buteyn-Peterson
furnish exact reasons for the county to grant a contract extension.
Mark Banton and Jim Uselding joined the meeting at
9:45 a.m.
Dreblow reviewed correspondence as follows:
City of Port Washington The committee is
invited to the August 17th Common Council meeting.
There will be a presentation by Ayres & Associates regarding
construction of a round a bout, at the CTH LL and STH 33
intersection compared to a signalized intersection, as part of the
STH 33 reconstruction project.
Human Resources Committee At its meeting
of July 14th the committee approved the replacement of
two Highway Department employees who are schedule to retire.
WisDOT The minutes of the STH 33 Public
Informational Meeting are available for review.
Annual Superintendents Conference The
conference is schedule for September 29th to October 1st.
In previous years three superintendents and three foreman have
been authorized to attend .
Moved by Grosklaus and second by Hilber to authorize six employees
to attend the WCHA Superintendent and Foreman Convention in
Appleton. All members present voting aye, the motion was adopted.
Dreblow reviewed the proposed 2005 budget for
buildings. Banton and Dreblow reviewed the propsed 2005 budget for
highway construction. The committee requested that Banton provide the
committee with the current average pavement condition rating at its
next meeting. The committee agreed to meet on August 2, 2004 to review
the entire 2005 proposed budget. Carroll will provide each committee
member a budget summary, for review, prior to the meeting.
Dreblow reviewed a fund transfer request of $23,700
for consultant fees for implementation of the new Great Plains Project
Accounting software.
Moved by Kletti and second by Grosklaus to approve the transfer
request. All members present voting aye, the motion was adopted.
The labor payroll of July 16, 2004 in the amount of
$79,482.48 was reviewed. Accounts payable batch #38170, in the amount
of $30,860.91, and batch #38172, in the amount of $118,037.36, were
reviewed. Moved by
Grosklaus and second by Kletti to approve accounts payable in the
amount of $148,898.27. All members present voting aye, the motion was
adopted.
Moved by Grosklaus and second by Kletting to
adjourn at 11:50 a.m. All members present voting aye, the motion was
adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
DRAFT
July 8, 2004
Port Washington, WI
Chairman
Kaul called the meeting of the Ozaukee County Highway Committee to
order at 9:00 a.m. Present were committee members Kaul,
Grosklaus, Uselding and Kletti, Commissioner Dreblow and Office
Manager Carroll. Hilber was excused.
Moved by Kletti and second by Grosklaus to approve the minutes of the
June 24, 2004 meeting as printed. All members present voting
aye, the motion was adopted. Chairman Kaul
recognized Tom Hartwig for his 20 years of service and Ron Weyker for
his 15 years of service, as equipment operators.
Dreblow
reviewed correspondence as follows:
-
WisDOT Connector
Express 2004 traffic fatalities, to date, are
14% less than in 2003.
-
Transportation
Survey Fran Myers forwarded a survey regarding
transportation. Results were almost evenly divided between
more and better highways and improved mass transit.
-
PDI
Town of Grafton planner Shawn Mularkey is considering construction
of a road between CTH C and Lakefield Road, east of I-43 and west
of the railroad tracks, to access parcels north of the County CTH C
Park & Ride Lot. Dreblow and the committee agreed that the
county would review the proposal as details become available.
-
Annual
Superintendents Conference The conference will
be held September 29th to October 1st at
Wisconsin Dells. In prior years the three superintendents and
three foreman attended. Dreblow requested the committee
approve sending six employees to the conference. Kaul
suggested that the item be considered at the next meeting of the
full committee.
-
Fill Vacant
Positions Interviews have been completed.
It appears that there will be two vacancies, in addition to the
previously authorized replacement. Dreblow will attend the
July 14th Human Resources meeting regarding those
replacement positions.
Superintendent Leppla joined the meeting.
Construction
and Maintenance projects were reviewed as follows:
-
CTH T and CTH W
Intersection reconstruction The intersection was
opened to traffic today. Scott Solverson (Earth Tech) will
attend the next highway committee meeting to review project costs.
Dreblow estimates that the project will come in under the $750,000
budget. The committee directed Dreblow to install stop signs
on trombone arms, for east and west bound traffic.
-
Seal Coat Projects
All seal coating has been completed. A polymer asphalt was
used on CTH W from Glen Oaks to CTH T. The material was
supposed to set up quickly. Three days later pavement
temperatures reach 115°
and tracking occurred. It was necessary to spread additional
cover material. Meigs is investigating the problem.
-
Centerline Painting
Uselding ask for a detailed explanation as to how signing and
coning is done in conjunction with painting. Dreblow and
Leppla explained how a sign van follows the paint truck to cone the
painted line immediately. Uselding reported that he had
received a complaint that wet paint was either not being coned or
the cones were picked up before the paint was dry. Staff will
follow up to determine that proper procedures are used.
Leppla
distributed copies of the proposed 2005 equipment purchases. The
committee reviewed the proposed purchases for inclusion in the draft
2005 budget.
Dreblow
advised Administrator Meaux of the Highway Committees concerns
regarding a new county logo.
The labor
payroll of July 2, 2004 in the amount of $83,642.85 was approved.
Accounts payable batch #38078, in the amount of $96,273.30 and batch
#38082, in the amount of $51,424.91 were reviewed.
Moved by Grosklaus and second by Kletti to approve accounts payable in
the amount of $147,698.21. All members present voting aye, the
motion was adopted.
Moved by Grosklaus and second by Kletti to adjourn to closed session
pursuant to Wisconsin Statutes 19.85 (1) (g) to discuss with legal
counsel, strategy with regard to possible litigation involving
right-of-way acquisition. Kaul, Grosklaus, Uselding and Kletti
voting aye, the motion was adopted.
The meeting
adjourned at 12:00 noon.
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
June 24, 2004 Draft
Port Washington, WI
Vice Chairman Grosklaus called the meeting of the
Ozaukee County Highway Committee to order at 9:00 a.m. Present were
committee members Grosklaus, Hilber, Uselding and Kletti, Commissioner
Dreblow, Office Manager Carroll, County Administrator Meaux and City
of Mequon Engineer Bill Hoppe. Chairman Kaul was excused.
Moved by Uselding and second
by Kletti to approve the minutes of the June 11, 2004 meeting as
printed. All members present voting aye, the motion was adopted.
Dreblow reviewed correspondence as follows:
Canadian National Railroad The railroad
will hold a meeting in Plymouth on 6/24/04 at 1:00 p.m. to discuss
the decision to abandon the rail line north of Saukville.
WisDOT Connector Express The Marquette
Interchange reconstruction project is on schedule and on budget.
WE Energies A request to continue renting
storage space at the Pinnacle site. Rent is $200 per month. The
committee directed Dreblow to agree to the request.
Contract Arbitration A decision has been
handed down in favor of the Countys offer.
SEWRPC It is time to update the 2020
Transportation Plan. County Board Chairman Brooks has appointed
Dreblow to be the Ozaukee County representative on the review
committee.
The committee agreed to address the agenda item CTH
W schedule out of order.
CTH W Glen Oaks to STH 167 Dreblow
explained that he met with Mequon officials and staff regarding
the proposed schedule for the project. Both participants in the
project would like the project to move more quickly. A meeting
with the consultant was scheduled for June 23rd. It is
expected that plans will be 60% complete in July and a meeting
will be scheduled with the Highway Committee for review. A
preliminary right-of-way plat should also be ready at that time.
Dreblow would like to engage a right-of-way acquisition firm at
this time. Moved
by Kletti and second by Uselding to direct Dreblow to negotiate
with Miesbauer & Assoc. for right-of-way services. All members
present voting aye, the motion was adopted.
Dreblow is optimistic that acquisition can begin in October. If
acquisition is completed in a timely basis the project could be
let to bid in December of 2005 with construction in 2006. Kapur
has completed a traffic study of the Glen Oaks and CTH W
intersection. Some warrants for signals have been met. Kapur will
include signal design as part of the project. The park and ride
lot at Venture Court is not part of the project but could be
constructed at the same time as the roadway. Hoppe left the
meeting.
Mark Banton joined the meeting. Banton represented
Dreblow at the June 16th meeting of the Traffic Safety
Committee. Jean Clement retired as chairperson. New officers are Fran
Myers, Chairperson and Chief Deputy Knowles, Vice-Chairperson. Ron
Schueller requested that the speed limit on CTH D be reduced to 45
mph. The Sheriff Department did a traffic study of the road and
determined that a lower speed limit was not needed. The committee
denied the request. Robert Clapper requested that the speed limit be
reduced on CTH T to 45 mph. The committee advised him that a traffic
study would be completed one year after the intersection of CTH W
and CTH T is completed.
Corporation Counsel Kenealy joined the meeting.
Dreblow reviewed other construction and maintenance
projects.
CTH T & CTH W Intersection Additional
soil excavation has added approximately $100,000 to the
construction costs. Paving will be completed this week. The
contractor will then complete his part of the reconstruction.
Chip sealing - CTH W from Glen Oaks to
CTH T is scheduled to be chip sealed on Saturday, June 26th.
Due to heavy weekday traffic volumes it will be more efficient to
perform the work on a Saturday.
STH 33 from Market to Tower WisDOT has
scheduled a 30% plan review meeting on July 7th at
Waukesha.
Summer Construction Projects Banton
distributed a schedule of projects. He will report to the
committee as projects are completed.
Waubeka Salt Shed The block walls are
complete. Trusses are scheduled for delivery the week of June 28th.
Policy on use of Park & Ride Lots A
request to erect a brat and beer stand in the park and ride lot at
CTH H and STH 57. The committee denied the request.
Moved by Hilber and second by Kletti park and ride lots be used as
intended, for public parking, not private events. All members
present voting aye, the motion was adopted.
Superintendent Tackes joined the meeting.
The proposed 5-year building plan was briefly
reviewed. Future agendas will have budget considerations for the 2005
budget.
The labor payroll of June 18th in the
amount of $74,632.38 was approved. Accounts payable batch #38001 in
the amount of $278,191.36, batch #38003 in the amount of $234,249.51
and batch #38012 in the amount of $4,580.76 were reviewed.
Moved by Kletti and second by
Uselding to approve accounts payable totaling $517,021.63. All members
present voting aye, the motion was adopted.
Dreblow reviewed the fund transfer request for the
unfunded pension liability.
Moved by Kletti and second by Hilber to approve the request. All
members present voting aye, the motion was adopted.
Moved by Uselding and second by Hilber to adjourn
to closed session pursuant to Wisconsin Statutes 19.85 (1)(g) to
discuss with legal counsel, strategy with regard to possible
litigation involving right-of-way acquisition. Hilber, Grosklaus,
Uselding and Kletti voting aye, the motion was adopted .
Moved by Kletti and second by Hilber to adjourn at
11:30 a.m. All members present voting aye, the motion was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
June 11, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 9:00 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow and Office Manager Carroll.
Moved by Uselding and second
by Kletti to approve the minutes of the May 27, 2004 meeting as
printed. All members present voting aye, the motion was adopted.
Superintendent Leppla joined the meeting.
Dreblow reported on the WCHA Summer Conference. At
the Bridge Committee meeting, WisDOT agreed to reconsider its
position on program manager training.
Waubeka Foreman Steve Paulus joined the meeting.
Chairman Kaul recognized Paulus for his 25 year as a Highway
Department employee.
Dreblow reviewed correspondence and communications
as follows:
Joe and Sharon Hawkins Letter The Hawkins
praised the efficiency of Highway Department employees in the
handling of tree removal and brush cleanup in the wake of the
severe thunderstorms and winds that struck Ozaukee County on May
21, 2004.
WisDOT Connector Express Traffic
fatalities decreased in May. It appears that motorcycle fatalities
have been reduced significantly due to the rainy spring weather.
Contract letting for the north leg of the Marquette Interchange
reconstruction project is July 27, 2004. Construction is expected
to begin in October.
County Logo The committee has concerns
regarding the proposed new county logo. The colored version of the
logo would match the existing Highway equipment, the irregular
shape probably would not remain attached to equipment and there
were concerns about the cost of the Highway department converting
to the new logo.
V & H Municipal Leasing Program Kaul
advised that V & H Trucks not has a municipal leasing program. He
suggested that it might benefit the county to lease instead of
purchase.
Dreblow reviewed construction and maintenance
projects.
CTH T and CTH W Intersection It
appears that the contractor will complete the final grading and
paving by the County can begin next week. If weather allows the
project should be completed on schedule.
STH 33 Reconstruction from Tower to Market
A public informational meeting was held at the Village of
Saukville on June 3, 2004. Preliminary plans call for a 4-lane
divided roadway with a 5 sidewalk on the south and a 10 of
pavement bicycle path on the north. There will be very few median
cuts, which will require right-turn only traffic movement at some
driveway and intersection locations. The engineering firm (Ayres &
Assoc.) will study the feasibility of constructing a round a bout
at the STH 33 and CTH LL intersection.
Waubeka Salt Shed Construction is
continuing. Approximately ½ of the block walls are complete.
Dreblow reviewed personnel items as follows:
At times the paving crew is short employees due
the having three permanent full-time employees scheduled on
Fridays. The Committee agreed that the Commissioner should adjust
the schedule as best suits the needs of the department.
Approximately 75 applications for the open
Equipment Operator position have been received. Three employees
have postponed their retirement dates because a labor contract
agreement has not been reached. The need to replace these
positions as soon as possible was discussed. Dreblow requested the
Committee approve replacement of these future retirees as soon as
they have given a firm date for their retirements.
Moved by Uselding and
second by Grosklaus to approve replacement of the anticipated
retirees. All members present voting aye, the motion was adopted.
Accounts payable batch #37860 in the amount of
$4,724.16, batch #37861 in the amount of $19,602.56, batch #37878 in
the amount of $5,131.75, batch #37904 in the amount of $34,938.46 and
batch #37909 in the amount of $31,435.97 were reviewed.
Moved by Kletti and second by
Grosklaus to approve the above accounts payable totaling $95,832.90.
All members present voting aye, the motion was adopted.
The labor payroll of June 4, 2004 in the amount of $72,946.29 was
approved.
Moved by Grosklaus and second by Hilber to adjourn
the meeting at 11:25 a.m. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
May 27, 2004Port
Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present wee committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow and Office Manager Carroll.
Moved by Grosklaus and second
by Kletti to approve the minutes of the May 13, 2004 meeting. All
members present voting aye, the motion was adopted.
Dreblow reviewed correspondence and communications
as follows:
WCHA Summer Highway Conference Kaul,
Hilber and Kletti confirmed that they would be attending. Carroll
distributed room reservation confirmation numbers. Ozaukee County
did not present any resolutions for consideration at this years
conference.
Construction and maintenance projects were reviewed
as follows:
Intersection of CTH T @ CTH W The
contractor has until June 30th to complete the
construction project. This date allows for paving by the county.
STH 33 Bridge Replacement The proposed
route for the project detour is CTH O, between STH 33 and STH
60. It is estimated that the bridge will be closed to traffic for
only 2 or 3 days.
Moved by Grosklaus and second by Uselding to approve the detour
route. All members present voting aye, the motion was adopted.
A public informational meeting is scheduled for at the Saukville
village hall on June 3rd, from 5:00 p.m. to
7:00 p.m., for the STH 33 reconstruction progect, from Market
Street (Village of Saukville) to Summit Drive (City of Port
Washington).
Waubeka Salt Shed The committee discussed
reducing the wall height by approximately 4. This reduction would
result in a cost savings of between $8,000 and $10,000.
Moved by Grosklaus and
second by Hilber to construct the shed to the original design
height. Grosklaus, Hilber, Uselding and Kletti voting aye, Kaul
voting nay, the motion passed.
2004 Bridge Inspections WisDOT has
interpreted that the county bridge inspection program manager must
be certified and have 10 years of bridge inspection experience.
Neither Dreblow nor Banton meet these requirements. G.A.S.
currently inspects all county and local bridges, bi-annually, at a
cost of $6,000. G.A.S. will act as the county bridge inspection
program manager at an additional cost not to exceed $1,000.
Moved by Grosklaus and
second by Uselding to hire G.A.S. to inspect all bridges and to
act as program manager. All members present voting aye, the motion
was adopted. The committee
discussed whether the Highway Department should charge local
government for the inspection services.
Moved by Grosklaus and
second by Kletti to continue to provide this service to local
governments at no cost to the locals. All members present voting
aye, the motion was adopted.
W B Corp has been paid in full for the construction
of the Cedarburg addition. Bonestroo will reimburse the county $575.00
toward the final payment.
Accounts Payable batch #37787 in the amount of
$55,464.25, batch #37809 in the amount of $40,105.33 and batch #37810
in the amount of $56,960.69 were reviewed.
Moved by Kletti and second by
Uselding to approve accounts payable totaling $152,630.27. All members
present voting aye, the motion was adopted.
The labor payroll of May 21st in the amount of $67.497.75
was approved.
Dreblow reviewed the $8,500 fund transfer of
request for the purchase of 17 additional radios. Slightly used radios
are available at approximately 1/3rd of their original
cost. Moved by Hilber
and second by Grosklaus to approve the transfer request. All members
present voting aye, the motion was adopted.
The committee agreed to schedule the next meeting
at 9:00 on June 11th so that the Buildings Committee could
meet prior to the Highway Committee meeting.
Moved by Uselding and second by Grosklaus to
adjourn the meeting at 10:30 a.m. All members present voting aye, the
motion was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
May 13, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow, Office Manager Carroll. Kaul pointed out that the minutes of
April 29, 2004 did not indicate which county highway would be paved in
2004. Carroll will correct the minutes to show that three segments of
CTH I will be improved and paved.
Moved by Grosklaus and second
by Uselding to approve the minutes of the April 29, 2004 meeting as
corrected. All members present voting aye, the motion was adopted.
Dreblow reviewed correspondence and communications
as follows:
Flag Day Committee The department has again
been invited to participate in the Flag Day Parade on June 13, 2004.
Employees volunteer their time for this event.
Monthly Conference Attendance The committee
signed the monthly conference attendance sheet.
Commissioners Training Dreblow attended the
Annual Commissioners Training at Waupaca on April 28th
and 29th. Dreblow reported that 18 counties are operating
asphalt production facilities. 5 counties, with all requiring some
type of matching funds, provide Town Road Aids. The legality of
counties doing work for other governments was addressed. Ozaukee
County is following proper procedures when doing work for other
governments.
District #2 Commissioners Meeting WisDOT
expenditures by activity were reviewed. More of the maintenance
budget is being spent on litter pick-up than on winter maintenance
of highways. There may be some discretionary funds available for
2004 projects.
Superintendent Tackes joined the meeting. David
Schwengel, rail safety analyst, also joined the meeting.
Schwengel was a rail safety investigator for the
Office of the Commissioner of Railroads. Although now retired, he is
completing the reports for the investigation and safety
recommendations for Ozaukee County and Washington County rail
crossings, completed prior to his retirement. Two rail lines run
through Ozaukee County. They are the Canadian National-Wisconsin
Central, through Mequon, Cedarburg, Grafton, Saukville and Fredonia,
and the Union Pacific, through Mequon, Grafton, Port Washington and
Belgium. The safe speed of trains is determined by the condition of
the tracks and the type of crossing. Schwengel recommends that
crossings be replaced where needed, safer signals be installed, and
that vision corners and sight distances are cleared and that accurate
traffic counts are conducted. Schwengel recommends that Ozaukee County
join the East Wisconsin Rail Consortium, in order to become more
involved in railroad safety.
Moved by Uselding and second
by Grosklaus that a letter be sent to the Office of the Commissioner
of Railroads, supporting Schwengels findings and recommendations in
Docket #9164INV525, Docket #9040INV1173 and Docket #9040INV1168. All
members present voting aye, the motion was adopted.
Schwengel left the meeting.
Tackes reported on his attendance at the North
American Snow Conference. Tackes believes that the conference was very
beneficial. Round table discussions with other attendees were very
informative. Some states are using anti-icing chemicals on the entire
length of roadways, prior to the actual snowfall. Considerable
research is being conducted on various chemical mixtures that could be
used for pre-wetting roadways. Tackes left the meeting.
Dreblow reviewed construction and maintenance
projects as follows:
CTH T at CTH W Intersection Removal of
the original concrete has resulted in the determination that there
is no gravel base under the existing roadway. It is necessary to
construct a base and to undercut the excess ground. This will be an
addition to the current construction contract. The underground
septic tank located under the roadway has been removed. Dreblow
allowed WE Energies to route the gas main around the tank, outside
the right-of-way.
Moved by Grosklaus and second by Kletti to grant WE Energies an
easement, on the southwest corner of the intersection, to allow for
the installation of the gas main. All members present voting aye,
the motion was adopted. Pay
request #2 has been received. Dreblow will review the request and
schedule it for payment.
STH 167 - I43 to STH 57 WisDOT has
scheduled a Public Informational Meeting for May 20th at
the Mequon city hall.
CTH W STH 167 to Glen Oaks The project
schedule has been updated. The final design should be complete in
November of this year. The estimated date for completion of the ROW
plat is October 2005. This date appears to be excessively
pessimistic. Dreblow has requested Kapur to reexamine its schedule
to see if the ROW plat could be completed in early 2005.
Waubeka Salt Shed Construction is
proceeding. Steve Paulus, Waubeka foreman, has requested that the
committee reconsider the proposed height of the building. Grosklaus
stated that he believes that the structure capacity should remain
3,400 tons, as planned. The committee took no action.
CTH I at Cedar Creek Turn lanes will be
constructed as a maintenance project.
CTH C at CTH W Superintendent Banton is
preparing plans for the construction of an eastbound to southbound
turn lane. Relocation of the existing signals will be necessary.
This cost is unknown at this time. There are no funds in the 2004
budget for this proposed project.
WisDOT 6-Year Plan Dreblow reviewed the
6-year plan. The only project for County Highways, in the plan, is
the reconstruction of CTH W from STH 167 to Glen Oaks.
Hilber left the meeting.
Members of the Highway Committee have been
appointed to both the Transit Committee and the Buildings Committee.
Dreblow proposed that the next meeting of these committees be
scheduled to begin immediately before the next two Highway Committee
meetings.
Accounts payable batch #37649 in the amount of
$28,626.79, batch #37650 in the amount of $19,071.26, batch #37718 in
the amount of $26,734.45 and batch #37721 in the amount of $46,343.88
were audited and approved for payment. The labor payroll of May 7,
2004 in the amount of $67,283.45 was approved.
Moved by Kletti and second by Grosklaus to adjourn
the meeting at 11:45 a.m. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
April 29, 2004Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:35 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Construction
Superintendent Banton and Account Clerk Learned.
Kaul asked for nominations for Chairman.
Moved by Kletti and second
by Hilber to nominate Kaul as Chairman. Grosklaus closed the
nominations. All members voting aye the motion carried and Kaul was
declared Chairman.
Kaul asked for nominations for Vice-Chairman.
Moved by Uselding and second
by Kaul to nominate Grosklaus as Vice-Chairman. Hilber closed the
nominations Kaul seconded closing. All members voting aye the motion
carried and Grosklaus was declared Vice-Chairman.
Kaul asked for nominations for Secretary.
Moved by Grosklaus and
second by Hilber to nominate Uselding for Secretary. All members
voting aye the motion carried and Uselding was declared Secretary.
Moved by Uselding and second by Kletti to approve
the minutes of the April 15, 2004 meeting as printed. All members
present voting aye, the motion was adopted .
Bill Janeshek joined the meeting at 8:45 a.m.
Correspondence and Communications were reviewed.
Uselding questioned the speed reduction at STH.
57 and Cth. A intersection to 45 mph.
Uselding questioned the barricade on Cth. T
(west of Wauwatosa Rd.). Banton said there was a gas valve
protruding in road.
Kaul mentioned Ulao Parkway chipseal/blacktop
coming off. Janeshek stated a thin mat was put on approx. 10 yrs.
ago.
Note from Bill Leppla Brake & Equipment was
bought by AM Equipment. AM Equipment cannot provide Heil dump
bodies so Leppla will go with 2nd low bid for 15 Yd.
Dump Body at $ 6,669.00 from Casper Truck which is $11.00 higher.
AM Eqt will not be invited to bid in 2005.
Update on traffic counts on STH. 181 Letter
from Bob Anderson stating traffic trend was 6,122 daily for the
past 10 years but an actual count will be taken during 2004.
Banton stated Dave Schwengel stopped earlier
this week and is requesting to be on next highway agenda regarding
R.R. Crossing report.
Banton checked who will be attending Summer
Highway Conference June 7, 8 and 9 at Chula Vista at Wisconsin
Dells. Kaul, Uselding, Hilber and Kletti are planning on
attending. Grosklaus will not.
Ron Schueller joined meeting at 9:05 a.m. Also
joining Regina Bares, Bert Bares, Leona Bares, Ed Bares and Robert
Bares
Ron Schueller has requested a variance to county
access control ordinance. He would like 3 access points to his
property on Hwy. D for the purpose of developing six lots. Schueller
wants speed reduction to 45 mph which would allow for 3 access points
(one every 300). Current 55 mph speed only allows one driveway every
500. Kaul had informed him previously to speak with Chief Knowles to
get on agenda of Traffic & Safety Committee for lowering the speed
limit. Schueller wasnt sure when that would occur. Clarified to
Schueller to make sure this is on next Traffic & Safety Committee
agenda, June 9th. for their approval before Highway
Committee could consider the variance. Some discussion by Uselding for
a frontage road but Schueller stated that would move lots into
floodplain. Motion
made by Grosklaus & second by Hilber
to deny the request
for a variance. All members present voting aye the motion to deny a
variance was approved. Schueller &
neighbors listed above, left meeting at 9:40 a.m. Account Clerk
Verheyen joined the meeting at 9:40 a.m.
The proposed Gravel price for 2004 was $5.00 per
ton. Last years price was $4.90. After some discussion,
it was moved by Grosklaus and
second by Kletti to set the 2004 price for Gravel at $5.00 per ton.
All members present voting aye, the motion was adopted.
The proposed hot mix price for 2004 was $24.75 per
ton. Last years price was $23.70 per ton. After some discussion,
it was moved by Kletti
and second by Hilber to set the 2004 price for Hot mix at $24.75 per
ton. All members present voting aye, the motion was adopted.
Superintendent Banton went thru the 2004 Paving
Projects for the County Trunk Highways:
CTH I - Shady Lane to Hawthorne This
segment will be pulverized and reconstructed from 22 wide
pavement to 30 wide pavement, at an estimated cost of $212,000.
CTH I - Hawthorne to River Park This
segment is to be reconstructed from 22 wide pavement to 30
wide pavement with a 2 ½" overlay and 4" paved shoulders, at an
estimated cost of $100,000.
CTH I - River Park to CTH "H" This
segment is to be reconstructed from 22 wide pavement to 30
wide pavement with a 2 ½" overlay and 4" paved shoulders, at an
estimated cost of $100,000.
Intersection of "T" & "W" - This will be done
in conjunction with the reconstruction at an estimated cost of
$100,000.
The Other Paving Projects are as follows:
Harrington Beach Parking Lot Expansion This
is a full construction project adding 24 parking stalls at an
estimated cost of $30,000.
Ice Arena Parking Lot Expansion This is a
full construction project carried over from 2003 and will be
done at an estimated cost of $50,000.
Town Roadwork This will be done with a 50%
match of the Town Road Aids, at an estimated cost of $262,000.
The Chip Seal Projects are as follows:
CTH "P" This will be the entire length of
CTH "P" using pea gravel at an estimated cost of $14,000.
CTH "W" This will be done from STH "33" to
STH "57", at an estimated cost of $26,000.
CTH "W" This will be done from Glen Oaks to
CTH "T", at an estimated cost of $50,000.
Superintendent Banton stated that the Highway
personnel were pouring the footings for the walls on Thursday, April
29, at the Waubeka Salt Shed. They are doing an excellent job of
putting up the Salt Shed. Everything is on track.
Superintendent Banton stated that the contractor
for the reconstruction of the intersection on CTH "T" and "W", Buteyn-Peterson,
had not been on the jobsite for the past two weeks. Karl Nauschultz of
Earth Tech was contacted about the situation and will be handling it.
Numerous phone calls have come into the Highway Office from citizens
who travel that road, complaining about the road being closed to
traffic and no work being done at that intersection.
The June 10th Committee Meeting has been
changed to June 11th, 2004 because of a conflict with the
Summer Highway Conference, which runs from June 8th to June
10th.
The labor payroll of April 23rd, 2004 in
the amount of $68,245.16 was approved.
Moved by Kletti and second by
Hilber to approve accounts payable batch #37610 in the amount of
$1,459.36 and batch #37611 in the amount of $96,692.23. All members
present voting aye, the motion was adopted.
Moved by Hilber and second by Uselding to adjourn
the meeting at 11:30 a.m. All members present voting aye, the motion
was adopted.
Respectfully Submitted,
Kathy Learned & Debbi Verheyen
Account Clerks
Table of Contents
April 1, 2004
Port Washington, WI
DRAFT
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus and Uselding, Commissioner Dreblow,
Office Manager Carroll, Patrol Superintendent Tackes and Mequon City
Engineer Bill Hoppe. Superivisor Kletti was excused.
Moved by Hilber and second by
Grosklaus to approve the minutes of the March 18, 2004 meeting as
corrected. All members present voting aye, the motion was adopted.
Kaul advised Dreblow that Robert Clapper was not prepared to meet with
the committee and requested that he be scheduled for the meeting of
April 15, 2004. Dreblow reported that construction of the intersection
of CTH W at CTH T has begun and that the intersection is closed to
through traffic.
Dreblow reviewed correspondence and communications
as follows:
Wisconsin Central Railroad The railroad
will no longer use the rail line north of Charter Steel.
Agreement Summary Dreblow reviewed the
proposed agreement and conservation easement with the Town of
Saukville, regarding gravel pit and asphalt plant operation.
Contract Arbitration Final rebuttal briefs
are scheduled for exchange. A decision is expected in May or June.
The prohibitive practice appeal has been placed on hold until the
contract arbitration is decided.
Right-of-Way Compensation Mediation The
court has ordered that compensation for right-of-way acquired for
the CTH W & CTH T intersection be mediated. Former Judge Walter
Swietlik has been appointed mediator. Meetings will be scheduled for
the Minor and Clapper properties. The mediation is non-binding.
WisDOT A letter from Transportation
Secretary Busalacchi, advises counties that the 2003-04-winter
season was very costly for WisDOT. A budget shortfall of $10,000,000
is expected.
Dreblow reviewed construction and maintenance
projects as follows:
CTH W Glen Oaks to STH 167 The
right-of-way plat should be completed in 2004 with acquisition in
2005. (Hoppe left the meeting.)
CTH T Robert Clapper is proposing a
residential development with access to CTH T. The location of
existing driveways results in the proposed access being in
non-compliance with the County Access Control Ordinance. The
committee reviewed a drawing the the proposed development.
CTH T & CTH W Intersection Dreblow and
Meaux are continuing to pursue the use of the Hazard Elimination
grant for funding the project. Dreblow has requested in writing the
specific requirements that may need a waiver in order to use the
grant.
2004 Summer Schedule Dreblow requested the
committee approve the summer schedule that is similar to last years.
Three equipment operators, three temporary employees and two shop
employees will work Tuesday through Friday. All other employees will
work Monday through Thursday, excepting the week of July 4th.
Moved by Uselding
and second by Grosklaus to approve the summer schedule as described.
All members present voting aye, the motion was adopted.
County Board Chairman Wirth joined the meeting to
discuss the town of Saukville agreement. Wirth will include a cover
letter, with the meeting packet, to all members of the County Board.
The letter will include the history of the gravel pit, crushing and
asphalt plant operations, and the proposed agreements with the Town of
Saukville. Wirth left the meeting.
Waubeka Foreman Paulus joined the meeting. He is
waiting for one additional proposal for steel. The Town of Fredonia
has issued the building permit. State approval of the plans is
expected shortly. Paulus left the meeting.
Shop Superintendent Leppla joined the meeting.
Leppla reviewed the excavating machine bids opened at the March 18th
meeting. Leppla recommended that the Caterpillar M316C be purchased.
The town of Cedarburg has submitted a request to purchase Cruz Air
#310 for $12,500.
Moved by Grosklaus and second by Hilber to accept the bid of Fabco for
a Cat M316C excavator, with no trade-in, at a cost of $132,696 and to
sell Cruz Air #310 to the town of Cedarburg for $12,500. Kaul, Hilber
and Grosklaus voting aye, Uselding voting nay, the motion was adopted.
Leppla left the meeting. Uselding left the meeting.
Dreblow reviewed the fund transfer, for the
construction of the salt shed at Waubeka and additional reconstruction
of CTH I in 2004.
Moved by Grosklaus and second by Hilber to approve the fund transfers.
All members present voting aye, the motion was adopted.
Moved by Grosklaus and second by Hilber to approve
accounts payable batch #37375 in the amount of $18,174.40, batch
#37405 in the amount of $543.98 and batch #37406 in the amount of
$22,976.53. All members present voting aye, the motion was adopted .
The labor payroll of March 26th in the amount of $71,427.80
was reviewed and approved.
Moved by Grosklaus and second by Hilber to adjourn
the meeting at 11:30 a.m. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
March 18, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:20 a.m. Present were committee
members Kaul, Hilber, Grosklaus and Uselding, Commissioner Dreblow,
Office Manager Carroll and Town of Saukville Supervisor Bill Niehaus.
Supervisor Kletti was excused. Also present was Karl Hokanson,
Earth-Tech architect.
Moved by Grosklaus and second by Hilber to approve the minutes of the
March 4, 2004 meeting as printed. All members present voting aye, the
motion was adopted. Waubeka foreman
Steve Paulus joined the meeting.
The committee agreed to alter the agenda in order
to address the Waubeka salt storage facility. Dreblow displayed a site
plan showing the location of the new building. He explained that
because there is unsuitable soil at the location of the current salt
shed, the location of the new building must be moved to the south. The
shed will be 60 x 90, with 16 poured concrete walls with concrete
block above that height. Glass blocks will be used above the poured
walls on the west and south walls, in order to allow daylight to
enter. The overhead door will not be centered in the north wall but
will be offset, in order to allow easier maneuvering of equipment
within the building. The maximum height will be 35. This height meets
the town of Fredonia zoning requirements. The committee discussed
various construction alternatives. (Single vs. multiple concrete
pours, treated vs. untreated steel rods) Current plans call for
highway employees to do the actual construction except for overhead
door installation and electric hookup. Hokanson and Paulus explained
that steel prices are increasing and that they hoped to place the
order for steel as soon as the committee approved the plans.
Moved by Uselding and second
by Grosklaus to approve the plans as presented and to direct that
construction proceed. All members present voting aye, the motion was
adopted. Hokanson and Paulus left
the meeting at 9:05 a.m.
Dreblow reviewed correspondence and communications.
Governor Doyle Dreblow read a letter
notifying Ozaukee County that the CTH W at CTH T intersection
reconstruction has been awarded funding, as a CHIP-D project.
WisDOT Connector Express Rustic waysides
and tourist information centers, previously scheduled for
elimination, will remain open.
County Traffic Safety Committee At the
meeting of March 10, 2004, traffic fatalities, which occurred in the
previous quarter, were reviewed. The committee recommended
additional signage at the intersection of CTH C at CTH T. WisDOT
will lower the speed limit on STH 57 at its intersection with CTH
H.
First Friday Meeting Hilber reported that
the topic, future transportation needs, was very informative.
Access Permit Variance Kaul reported that
Mr. Schueller would like to sub-divide his property on CTH D, but
that his plans are not compatible with the County Access Control
Ordinance. Kaul informed Mr. Schueller that it was very unlikely
that the Highway Committee would grant a variance for access.
Dreblow reviewed construction projects.
CTH T at CTH W Intersection A
pre-construction meeting was held on March 17, 2004. Utility work is
progressing. The contractor is scheduled to begin pavement milling
and storm sewer construction on March 29, 2004. The house on the
southwest corner has been sold and will be moved by the buyer.
Dreblow discussed the hazard elimination grant awarded to the
project. At this time WisDOT will not allow the grant funds to be
used because the WisDOT letting process was not followed. Instead
the project was bid locally. Dreblow explained that the date of the
original grant application was November 2002. Dreblow contacted
WisDOT on numerous occasions and was told that it was very unlikely
the project would be approved. The county proceeded with planning
the reconstruction as a local project. On March 8, 2004 the County
was notified that the grant had been awarded. Administrative
Coordinator Meaux is working with local legislators to obtain a
waiver from WisDOT that would allow Ozaukee County to use the grant
on the project.
Moved by Uselding and second by Grosklaus that the grant be accepted
and that Dreblow execute the necessary paper work. All members
present voting aye, the motion was adopted.
County Board Chairman Wirth, Administrative
Coordinator Meaux, Superintendent Banton, Foremen Bonjean and Janeshek
joined the meeting.
Shop Superintendent Leppla joined the meeting. Bids
for a rubber-tired excavator were opened as follows: BID
Trade-in Net Cost
Roland Machinery No Bid
American State Equip. Co. Liebherr $166,653.
$15,000 $151,653
Aring Equipment Co. Inc. Volvo-W-180B 129,934
8,000 121,934
Miller-Bradford & Risberg Badger-1085C 171,920
25,300 146,620
Miller-Bradford & Risberg Badger-1085D 175,280
25,300 149,980
Fabco Equipment Cat M316C 127,086 12,500
114,586
Leppla will review the bids and make a
recommendation to the committee at its next meeting.
Leppla reviewed the March 4th bids for a
road sweeper. Leppla recommended that the committee accept the bid of
Aring Equipment. The machine bid by Wisconsin Lift Truck was not
available for inspection and the machine bid by Miller-Bradford &
Risberg did not meet the departments needs.
Moved by Grosklaus and second
by Hilber to accept the bid from Aring Equipment for a Broce RC350
Sweeper at a cost of $27,773.00. All members present voting aye, the
motion was adopted. Leppla, Bonjean
and Janeshek left the meeting.
Dreblow, Meaux, Wirth and Niehaus reviewed the
proposed agreement and conservation easement between Ozaukee County
and the town of Saukville regarding the continued use by the County of
the crushed gravel and asphalt production sites in the town.
Moved by Uselding and second
by Grosklaus to accept the agreements with the understanding that
Niehaus will try to remove or modify the conservancy easement on
Parcel C1. The roll was called. Kaul, Hilber, Grosklaus and Uselding
voting aye, the motion was adopted.
Wirth reported that the Technical Resources
Department would be working with the Land Information Office to
digitally map the entire county. Some of the information could be
beneficial to Highway.
Wirth and Meaux left the meeting.
Dreblow reported that briefs have been exchanged
for the labor contract arbitration. The arbitrator is waiting for
responses from the County and O.P.E.I.U.
Grosklaus has received complaints regarding the
condition of the concrete portion of CTH V between Arrowhead Road
and the southbound I-43 ramps.
Moved by Grosklaus and second by Hilber to approve
accounts payable batch #37289 in the amount of $32,666.52, batch
#37317 in the amount of $53,402.74 and batch #37318 in the amount of
$43,379.55 . All members present
voting aye, the motion was adopted. The labor payroll of March 12,
2004 in the amount of $74,256.73 was approved.
Moved by Hilber and second by Grosklaus to adjourn
the meeting at 11:45 a.m. All members present voting aye, the motion
was adopted.
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
February 19, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow and Office Manager Carroll. Also in attendance were
Administrative Coordinator Meaux, Superintendent Bill Tackes and
County Board Supervisor Gerald Walker.
Moved by Hilber and second by
Kletti to approve the minutes of the February 5, 2004 meeting as
printed. All members present voting aye, the motion was adopted.
The committee signed the request for approval for Tackes to attend the
out-of-state North American Snow Conference in Lexington, KY.
Dreblow reviewed correspondence and communications
as follows:
WisDOT Connector Express A preliminary
information meeting for reconstruction of the Marquette Interchange
will be held at the War Memorial Conference Center in Milwaukee on
March 24, 2004, from 3:00 p.m. to 8:00 p.m. This past January had
the highest traffic fatality rate since January of 1966.
Aegis Wisconsin County Mutual has issued
Ozaukee County, based on loss control, a credit of $7,897 to its
deductible fund.
Tree Harvest Algoma Lumber will be unable
to access the Pinnacle site until late 2004, in order to selectively
harvest the woodlot.
WisDOT The County has been ordered to
convey the right-of-way for STH 57 properties back to the state.
Moved by Uselding
and second by Hilber to direct Dreblow sign the quitclaim deeds for
the eight parcels. All members present voting aye, the motion was
adopted.
WCHA Summer Roadeo Dreblow requested that
the committee approve sending the three foremen to this years state
roadeo. Moved by
Uselding and second by Grosklaus to send the foremen. All members
present voting aye, the motion was adopted.
Annual Report to the County Board Dreblow
distributed copies of the annual report. A summarized version will
be presented to the County Board at its meeting on April 7, 2004.
County Board Chairman Wirth joined the meeting.
Moved by Grosklaus and second by Uselding to
adjourn to closed session, at 9:15 a.m., for the purpose of discussing
potential litigation, pursuant to Wisconsin Statutes 19.85 (1) (g).
The roll was called. Kaul, Hilber, Grosklaus, Uselding and Kletti
voting aye, the meeting was declared closed .
Moved by Hilber and second by Kletti to return to
open session at 10:15 a.m. The roll was called. Kaul, Hilber,
Grosklaus, Uselding and Kletti voting aye, the meeting was declared
open .
The committee tentatively scheduled their next
meeting for Tuesday, March 2nd at 8:30 a.m., if a special
meeting is needed prior to the March 3, 2004 County Board Meeting
Wirth, Meaux and Walker left the meeting.
Dreblow reviewed construction and maintenance
projects.
CTH T and CTH W Intersection County
crews have removed shrubs and brush in order to allow utility
companies access to the right-of-way so that utilities can move
their facilities prior to the contractor beginning the
reconstruction project. Dreblow reviewed a tentative agreement for
construction oversight services by Earth-Tech. The contract would be
based on time and materials and the estimated cost is $61,000.
STH 33 Operational Planning Meeting
WisDOT has tentatively scheduled the reconstruction from Tower Dr.
to Market Street for 2009. This is adding an additional two years to
the project timeline. None of the municipalities present at the
meeting were pleased with this announcement. There are a number of
items recommended by SEWRPC that are not being addressed as part of
the project. WisDOT would like to see the road as a connecting
highway. There are currently no plans to remove the bridge over CTH
LL as a separate project.
WisDOT Dreblow reviewed the DMA for sign
maintenance in the amount of $17,000.
Moved by Grosklaus and
second by Kletti to accept and sign the DMA. All members present
voting aye, the motion was adopted.
Superintendent Leppla, Foreman Janeshek and Foreman
Bonjean joined the meeting. Leppla reviewed his analysis for the
tractor/mower bids opened at the meeting of February 5, 2004. The
lowest bids were for a tractor that has never had a mower attachment
mounted on it. Leppla indicated that he is fearful of purchasing an
unproven piece of equipment. Leppla recommended accepting the bid of
Mid-State Equipment for purchase of two (2) John Deere Model 6415
Tractors, two (2) Diamond 60" Rotary Mowers and two (2) Diamond 102"
Flail Mowers at a total cost for two complete mowing units of
$108,540.00. Moved by
Uselding and second by Kletti to accept Lepplas recommendation and
accept the Mid-State Equipment bid. All members present voting aye,
the motion was adopted.
Leppla discussed the need to replace the current
Cruz-Air ditching machine that was purchased new in 1993. Leppla
reviewed the operating history and related his experience of what to
expect in maintenance costs if the current machine is not replaced.
There is $165,000 in the 2004 budget for replacement. Leppla asked the
committee if it is still in favor of replacing the machine.
Moved by Hilber and second by
Grosklaus that Leppla be directed to advertise for bids. Kaul, Hilber,
Grosklaus and Kletti voting aye, Uselding voting nay, the motion was
adopted. Leppla, Tackes, Bonjean and
Janeshek left the meeting.
Moved by Grosklaus and second by Kletti to approve
accounts payable batch #37098 in the amount of $23,682.61, batch
#37074 in the amount of $40,109.55 and batch #37092 in the amount of
$14,449.24. All members present voting aye, the motion was adopted .
The labor payroll of February 13, 2004 in the amount of $84,624.23 was
approved.
Moved by Grosklaus and second by Kletti to adjourn
the meeting at 12:15 p.m. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
February 5, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow, Superintendents Banton and Tackes and Administrative
Coordinator Meaux. Bill Gruenwald, town of Grafton, was also present.
The committee signed the conference attendance report.
Moved by Uselding and second
by Kletti to approve the minutes of the January 22, 2004 meeting as
printed. All members present voting aye, the motion was adopted.
Office Manager Carroll joined the meeting. Attendance sheets for the
WCHA Winter Highway Conference were signed.
Dreblow reviewed correspondence and communications:
WisDOT Connector Express-Special Edition
The Surface Transportation Program projects have been announced.
Approved Wisconsin projects total $75 million in federal
allocations.
WisDOT Connector Express Transportation
Director Busalacchi has appointed Paul Trombino as the director of
the Bureau of Structures.
Cedarburg Police Department Letter
regarding clarification of the way in which the citys weight
restriction ordinance will be enforced, with regard to County
highway Department equipment using city streets.
Ayres & Associate The operational planning
meeting for the STH 33 reconstruction project has been rescheduled
to 2/13/04.
Summer Highway Conference The conference is
scheduled to begin at 8:30 a.m. on June 8th. The room
reservations are for June 8th and 9th. Carroll
was directed to reserve rooms for the night of June 7th.
Winter Highway Conference Dreblow, Kaul,
Hilber and Kletti reported on the conference. Topics of interest
were the utility policy, contract work for local governments, the
Local Road Improvement Program, Machinery Management Committee rate
determination policy and state program for removal of car killed
deer.
UW Extension Road Maintenance Seminar
Dreblow and Tackes requested approval to send 4 employees to the
seminar. The main topic is pavement maintenance practices and
procedures. The committee suggested that only 2 employees be sent.
APWA North American Snow Conference This
year the conference is being held in Lexington, KY April 25th
thru April 28th. Dreblow requested the committee
authorize Superintendent Tackes to attend. Tackes is interested in
learning more regarding the use salt brine with other chemicals for
deicing. Moved by
Uselding and second by Grosklaus to approve 2 employees attend the
Road Maintenance Seminar and to approve Tackes attend the APWA
Conference subject to Finance Committee Approval. All members
present voting aye, the motion was adopted.
County Board Chairman Wirth joined the meeting.
Michael Kalnbach, Earth-tech, joined the meeting to
review the bids and provide a recommendation of award, for
construction of the CTH W and CTH T intersection, which were
opened on 2/3/04. Kalnbach distributed the bid results and his
recommendation to award the bid. Sealed bids were received from three
general contractors as follows:
Contractor Base Bid Alternate Bid
Buteyn-Peterson Construction Co., Inc. $340,883.51
$130,778.90
Musson Brothers, Inc. 378,496.99 133,478.90
Capitol Pavers, Inc. 415,850.88 130,778.90
Buteyn-Peterson has removed Streu-Gulseth from its
sub-contractors list due to the fact that Streu-Gulseth is on the
WisDOT suspended contractors list and state administered funding is
being used on the project. Kalnbach and Dreblow recommended that only
the base bid be awarded at this time and that the department provide
the paving called for in the alternate.
Moved by Grosklaus and second
by Kletti that Buteyn-Peterson has submitted the lowest responsive and
responsible bid, that the County accept the base bid of $340,883.51
and award the contract to Buteyn-Peterson for reconstruction of the
CTH W and CTH T Intersection and that Commissioner Dreblow be
authorized to execute the necessary documents. All members present
voting aye, the motion was adopted.
Dreblow will meet with Kalnbach to prepare a construction oversight
agreement and report back to the committee.
Wirth, Meaux and Kalnbach left the meeting.
Bill Grunwald appeared to express interest in
purchasing and moving the home located within the right-of-way of the
intersection. He informed the committee that he believes the tenant
will continue to occupy the house until June. Dreblow advised him that
the lease for the rental of the home requires the occupant vacate the
premises by March 1, 2004. Dreblow will consult the right-of-way
acquisition firm to determine if the occupant will indeed vacate the
premises per the lease agreement. Dreblow also advised Grunwald that
he would need to work directly with the general contractor if he
wishes to purchase the home and move it. Grunwald left the meeting.
Dreblow informed the committee that DNR Forester
Julie Peltier, Andy Holschbach and Merlin Depies walked the Pinnacle
property to inspect the trees marked for removal. The DNR agreed that
the marked trees should be removed. Dreblow reviewed the proposals for
selective harvesting as follows:
Krueger Lumber $5,600.00
Lakeshore Forest Products 9,010.00
Algoma Lumber 11,190.00
Moved by Kletti and second by Uselding to accept
the proposal from Algoma Lumber in the amount of $11,190.00. All
members present voting aye, the motion was adopted .
Superintendent Leppla joined the meeting. Dreblow
explained that employees have shown an interest in purchasing the
scrap heaters from the Waubeka shed and the damaged snow mobile
trailer, found three years ago. The committee will allow employees to
offer sealed bids for the items.
The 2004 budget ($150,000) allows for the purchase
of two tractor-mower units. Bids were opened from the following
vendors: Lochens Implement, F & I Equipment, Miller & Boeldt, Roland
Machinery, St. Lawrence Equipment, Serwe Implement, Waldo Implement
and Mid-States Equipment. Leppla will review the bids and prepare a
recommendation for the next committee meeting.
The 1-ton truck chassis budgeted for 2004 is
available through the Value Purchase program from Kayser Ford at a
cost of $18,887.00 for a Ford F350.
Moved by Kletti and second by
Hilber to purchase the truck. All members present voting aye, the
motion was adopted.
Leppla distributed a bid analysis for winter
maintenance equipment bids opened at the 1/22/04 meeting. Bids were as
follows:
Vendor 6yd SS 15 yd SS Hydraulic Pusher
Dump Dump Dump Dump System Axle
Body Body Body Body
Casper Truck
Equipment 2,879.00 4,867.00 6,669.00 13,992.00
2,956.00 13,068.00
Monroe Truck
Equipment 3,470.00 4,504.00 7,846.00 3,500.00
13,571.00
Brake &
Equipment 3,489.00 5,089.00 6,658.00 9,964.00
2,969.00 12,846.00
Vendor Reversible Hitch Wing Tailgate SS Pre-
Plow Plow Spreader Sprdr Wetting System
Casper Truck LH 4,100.00
Equipment 4,859.00 1,454.00 RH 4,100.00 2,284.00
2,966.00 2,320.00
Monroe Truck LH 4,219.00
Equipment 4,211.00 1,034.00 RH 4,219.00 2,276.00
3,050.00 2,282.00
Brake &
Equipment 2,395.00 3,143.00 2,194.00
Schmidt 5,190.00 LH 3,537.00
Engineering 5,120.00 1,917.00 RH 3,335.00
Leppla recommended purchasing the 3 yd. Stainless
steel dump body from Monroe Truck & Equipment at a cost of $4,504.00;
the 15 yd steel dump body from Brake & Equipment at a cost of
$6,658.00; the pusher axle from Casper Truck Equipment at a cost of
$2,956.00; the hydraulic system from Brake & Equipment at a cost of
$12,846.00; the reversible plow from Casper Truck Equipment at a cost
of $4,859.00; the snow plow hitch from Monroe Truck Equipment at a
cost of $1,034.00; the RH Wing at a cost of $3,335.00 and the LH Wing
at a cost of $3,537.00 from Schmidt Engineering; the stainless steel
tailgate spreader from Casper Truck Equipment at a cost of $2,966.00
and two pre-wetting systems from Brake and Equipment at a cost of
$2,194.00 for two units.
Moved by Grosklaus and second by Kletti to accept Lepplas
recommendations. All members present voting aye, the motion was
adopted.
Leppla advised the committee that the replacement
overhead garage door, at the Cedrburg shop, has been installed.
Accounts payable batch #36971 in the amount of
$11,360.29 and batch #36976 in the amount of $48,522.77 were reviewed.
Moved by Uselding and
second by Grosklaus to approve payment of the batches. All members
present voting aye, the motion was adopted.
The labor payroll of January 30, 2004 in the amount of $77,672.90 was
approved.
Moved by Kletti and second by Hilber to adjourn the
meeting at 12:15 p.m. All members present voting aye, the motion was
adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
January 22, 2004Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow and Office Manager Carroll. Superintendent Banton and Tackes
were also in attendance.
Moved by Kletti and second by Grosklaus to approve the minutes of the
January 8, 2004 meeting as printed. All members present voting aye,
the motion was adopted.
Dreblow reviewed correspondence and communications
as follows:
WisDOT Connector Express Traffic
fatalaties may now be tracked on the WisDOT web site. The number of
Amtrac passengers increased substantially in 2003.
City of Mequon The fatal accident at the
intersection of Granville Road (CTH Y) and Pioneer Road (CTH C)
is being investigated. The intersection is under the maintenance
jurisdiction of Mequon. If Mequon were to pass an ordinance making
the intersection a 4-way stop, the county would need to mirror the
ordinance.
WisDOT An effort will be made to pass
legislation to restore AB255.
WisDOT A list of 2003 accomplishments is
available for review.
Ayres An operational planning meeting for
the planned STH 33 reconstruction is scheduled for 2/10/04 and the
planned STH 33 Bridge construction is scheduled for 2/9/04.
Cedarburg Police Department A letter
reviewing the citys weight restriction enforcement policy.
The committee agreed to address the agenda item
regarding allowing a sign within the CTH W right-of-way. Steve Smith
and Bruce Moore appeared on behalf of Fire Ridge Golf Course and
requested the committee allow the neon sign, which was erroneously
errected within the right-of-way, to remain. Dreblow reviewed the fact
that plans were shown to he and Supt. Tackes with the proposed sign on
golf course property and not on the right-of-way. The distance between
the property line and the sign varies from 31 to 34. All parties
discussed various options to solve the issue.
Moved by Kletti and second by Hilber to direct Fire Ridge owners to
remove the sign from within the right-of-way by July 1, 2004. All
members present voting aye, the motion was adopted.
Smith and Moore left the meeting.
Administrative Coordinator Meaux and County Board
Chairman Wirth joined the meeting at 9:40 a.m.
Dreblow informed the committee that WisDOT has a
scheduling conflict and is unable to attend todays meeting. The
appearance is rescheduled to March 4th.
CTH I Reconstruciton - Dreblow announced
that the reconstruction and relocation of the intersection of CTH
I at STH 33 has been approved as a major Hazard Elimination
project. Project cost is estimated at $534,000 with the federal
share capped at $378,360. The local share would be approximately
$160,000. The right-of-way plat would most likely be completed this
summer, with acquisition in 2005. Wirth suggested budgeting the
project in 2005. Moved by Grosklaus and second by Uselding to direct
Dreblow to execute the aggreement and accept the grant of $378,360.
All members present voting aye, the motion was adopted.
Pinnacle site Arrangements are being made
to have a DNR representative mark the trees which need harvesting,
in order to manage the woods properly.
WisDOT Routine Mainenance Agreements The
WisDOT maintenance budget for 2004 is approximately $18,000 higher
than in 2003. Moved by
Kletti and second by Hilber to accept and sign the agreements. All
members present voting aye, the motion was adopted.
Superintendent Leppla joined the meeting. Bids were
opened for reversible plows, plow hitches, wing plows, tail-gate
spreaders, prewetting systems, hydraulic systems, dump bodies and a
pusher axle. Leppla will prepare an analysis of the bids for the next
committee meeing and will recommend which bids to accept at that time.
Leppla recommended the committee accept the bid
from Badger Truck for a Sterling chassis, with the Mercedes engine and
auto shift transmission, at a cost of $67,823.00. Moved by Uselding
and second by Grosklaus to accept the Badger Truck bid in the amount
of $67,823.00. Kaul, Hilber, Grosklaus and Uselding voting aye, Kletti
voting nay, the motion was adopted.
Leppla reviewed the following proposals for the
purchase of engine oil.
E.H. Wolf & Son Chevron 3.29/gal.
Plymouth Oil Citgo 2.99/gal.
E.H. Wolf & Sone Citgo 3.18/gal.
Corey Oil House Brand 2.86/gal.
Leppla explained that only chevron oil has been
used in the past. The Citgo oil is not equal to the Chevron oil and he
is reluctant to change brands.
Moved by Grosklaus and second by Uselding to accept the proposal from
E. H. Wolf for Chevron engine oil at a cost of $3.29 per gallon. All
members present voting aye, the motion was adopted.
Accounts payable batch #36818 in the amount of
$122.57 and batch #36848 in the amount of $54,149.71 were audited and
approved for payment. The labor payroll of January 16th in
the amount of $80,473.88 was approved.
Moved by Kletti and second by Grosklaus to adjourn
the meting at 12:00 noon. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
Table of Contents
January 8, 2004
Port Washington, WI
Chairman Kaul called the meeting of the Ozaukee
County Highway Committee to order at 8:30 a.m. Present were committee
members Kaul, Hilber, Grosklaus, Uselding and Kletti, Commissioner
Dreblow, Office Manager Carroll, Administrative Coordinator Meaux and
County Board Chairman Wirth.
Moved by Grosklaus and second by Kletti to approve the minutes of
the December 23, 2003 meeting as printed. All members present voting
aye, the motion was adopted. Superintendent Banton
joined the meeting
Dreblow reviewed correspondence.
Winter Highway Conference Dreblow
distributed the conference itinerary.
Fond du Lac County Dreblow read the letter
from Commissioner Winters thanking the department for its donation
to the family of the Fond du Lac County highway employee, who was
killed in a work zone traffic accident.
WisDOT Confirmation of 2004 General
Transportation Aids in the amount of $1,024,391.
WisDOT Explanation from Governor Doyle as
to why he vetoed AB255 (Pothole Liability Bill).
City of Cedarburg Dreblow read the new city
ordinance restricting heavy trucks from using city streets. The
ordinance does not apply to CTH C or STH 181.
CTH T and CTH W Intersection Reconstruction
Project Minor and Clapper are appealing the award of damages,
for right-or-way acquisition, in circuit court.
WisDOT Connector Express 2003 had the
highest number of traffic fatalities (837) since 1981 (927).
Village of Fredonia Letter requesting
reduced speed limits at the intersection of STH 57 and CTH H. The
Highway Committee has addressed this request and sent an ordinance
to the County Board to reduce the speed limit on CTH H.
Fire Ridge Golf Course Dreblow reviewed a
request for a variance to allow the golf course sign to remain on
the CTH W right-of-way. Dreblow and Supt. Banton reviewed the
history of the sign. The plan presented to Dreblow showed the sign
behind the right-of-way. Dreblow suggested issuing a revocable
permit in order to allow the sign to remain. The committee discussed
precedents. Banton will request the owner document the signs
location in relation to the right-of-way. The committee will address
the item at a future meeting. Banton, Meaux and Wirth left the
meeting.
Town of Belgium Kaul informed the committee
that the town is objecting to the implementation, by the Highway
Department, of a 4% administrative charge for monthly services
performed for local governments.
Superintendent Leppla joined the meeting. Leppla
opened bids for the purchase of a tri-axle truck chassis as follows:
Auto Shift Allison
V & H Trucks Sterling - Mercedes X $69,375.00
V & H Trucks Sterling Cat Engine X 74,737.00
V & H Trucks Sterling Cat Engine X 80,132.00
Badger Truck Sterling Mercedes X 67,823.00
Badger Truck Sterling Cat Engine X 73,099.00
Badger Truck Sterling Cat Engine X 81,921.00
Milwaukee Truck Center Mack X 77,900.00
Milwaukee Truck Center Mack X 86,250.00
Milwaukee Truck Center Volvo X 77,900.00
Milwaukee Truck Center Volvo X 86,250.00
Cooleys IHC X 69,799.00
Cooleys IHC X 55 73,789.00
Cooleys IHC X 65 74,389.00
Leppla will review the bids and make a
recommendation to the committee at its next meeting. Leppla reviewed
proposals for replacement of the upper-level and lower-level heating
units at the Waubeka shop as follows:
Mueller Heating $5,685.00
Bergin Heating $7,266.00
Moved by Grosklaus and second by Uselding to accept
the proposal of Mueller Heating to replace the heating units at
Waubeka at a cost of $5,685.00. All members present voting aye, the
motion was adopted.
Construction projects were reviewed.
CTH H - The village of Fredonia will annex
the right-of-way of CTH H to the village. The county will continue
as the maintenance authority for the highway.
Pinnacle Property Dreblow requested that
the committee approve selective harvesting of trees at the site. It
would be good resource management. Dreblow will discuss the plan
with the Planning, Management and Land Resources Department and
report back to the committee.
CTH T and CTH W Intersection Reconstruction
Bid opening will be 2/3/04, with an agenda item on 2/5/04 to
consider award of the contract.
The labor payroll of January 2, 2004 in the amount
of $72,946.68 was approved for payment. Accounts Payable batch #36686
in the amount of $108,781.18 was approved.
A request to transfer $20,000.00 from Cedarburg
Building Maintenance to the Cedarburg Shop Addition outlay for HVAC
was reviewed. Moved by
Uselding and second by Grosklaus to forward the request for the
transfer to the Finance Committee and the County Board for approval.
All members present voting aye, the motion was adopted.
Moved by Grosklaus and second by Kletti to adjourn
the meeting at 12:00 noon. All members present voting aye, the motion
was adopted .
Respectfully Submitted,
Georgia Carroll, Office Manager
|